New development! Lonovo Pharma plant cell fermentation super factory in China →

2024-06-22

In recent days, construction of the Langou Pharmaceutical Plant Cell Fermentation China Superfactory Project, with a planned total investment of RMB 3 billion, has been progressing steadily. Several workshops have already been topped out. The pilot-scale production workshop is expected to become operational by the end of the year, while the entire project is scheduled for completion and full operation by the end of the following year.


Construction Progress of the Superfactory


At the construction site, reporters observed transport vehicles moving back and forth, while excavators, tower cranes, and other machinery operated continuously, creating a bustling scene of construction activity.

The project is being developed in two phases, covering a total land area of approximately 200 mu (about 133,333 square meters). Phase I has a total construction area of approximately 100,000 square meters and consists of 14 buildings, including a pilot-scale production workshop, integrated warehouses, a medical aesthetics production workshop, a health products workshop, a quality inspection building, a comprehensive office building, a purification and refining workshop, fermentation workshops, and a utility building.


Superfactory Construction Site


The project comprises two major production sectors. The first is a GMP-compliant manufacturing base for active pharmaceutical ingredients (APIs), including paclitaxel and docetaxel.

The second is a research, development, and manufacturing base for core active compounds derived from medicinal plants such as ginkgo and notoginseng. Its product portfolio includes ginkgolide compounds, notoginseng saponins, functional foods, health products, and natural plant-based skincare products.


Plant Cell Fermentation Superfactory Project

Industrial Facility Construction


Currently, the pilot-scale production workshop has been topped out and is undergoing interior finishing work. The main structure of Integrated Warehouse No. 1 has also been completed, while foundation construction is underway for Integrated Warehouse No. 2 and the medical aesthetics workshop.

Jiang Zunzhong, the on-site project manager of the Langou Pharmaceutical Plant Cell Fermentation China Superfactory Project, stated that Phase I construction was approximately 30% complete.

The pilot-scale production workshop was expected to begin operation by the end of 2023, with an estimated output value of approximately RMB 25 million.

Integrated Warehouse No. 1, Integrated Warehouse No. 2, the medical aesthetics workshop, the comprehensive office building, and the quality inspection building were expected to become operational during the first half of 2024. The entire project was scheduled to commence operations by the end of 2024, with an estimated annual output value of approximately RMB 200 million.


Source: Excerpt from The Paper (October 9, 2023), Jiawang Release.